Project Datasheet

Warehouse & Distribution Market Sector

Project: True North  

For more details please contact:

Andrew Marston
Commercial Manager
Atlas Ward Structures Ltd
+44 (0) 1944 710421
estimating@atlasward.com
Client: Polestar Group Limited
Location: Sheffield

Country: England
Partners: Main Contractor: UK GSE Limited
Engineer: Burks Green
Architect:Braithwaite & Jackman
Statistics: Total Tonnage: 2,250 tonnes
Programme: 8 weeks
Completion Date:  September 2004
Overview: 'True North' is a print facility in Sheffield built for Polestar, the largest printing company in the UK.
This project measures 45,000m2 and weighs in excess of 2,250 tonnes of structural steel.

Atlas Ward Structures designed, fabricated and erected the hefty structural steel frame within a tight, fast-trak programme of 7 weeks.
       