Project Datasheet

Commercial Offices Market Sector

Project: More London Plot 3  

For more details please contact:

Peter Miller
Sales Contact
Severfield-Watson Structures Ltd
+44 (0) 1845 577 896
info@sfrplc.com
Client: More London Developments
Location: London
Greater London
Country: England
Partners: Management Contractor: Mace
Architect: Foster & Partners
Engineer: Arup
Statistics: Total Tonnage: 2,850 tonnes
Programme: 23 Weeks
Completion Date:  December 2005
Overview: As part of the More London development on the south bank of the Thames between London and Tower Bridges, Severfield-Reeve carried out connection design, fabrication and erection of structural steelwork. Along with the supply and fixing of metal decking, edge protection and steel stairs to this new London office development.

The 2,850 tonnes of fabricated steelwork included 1,775 tonnes of Fabsec beams with service holes profile cut into the webs, and was generally supplied with an off-site applied intumescent coating to give a 60 minute fire rating.

The project was a creditable health and safety performance with the Group's "Off-Load Safe" unloading procedure being used extensively.
       